Hi Limor,
Check the MRP run control parameter - Scheduling function. System considers Inhouse production time for Basic date scheduling and Routing time for lead time scheduling.
Also check the number of days maintained in Release period at material master Schedule Margin key if you expect the opening period to be on 25.01.14.
Regards,
Dharma