Dear Experts,
Currently our client is using the ECC 6. EHP6 TAXINN procedure is using.
Scenario :- 1
Material :- BB27AH30KC10191-01
Plant :- 1000
Vendor :- 100029
Creating the PO for the above combination and maintained the tax code as V1.
The same FV11 is maintained for JMOP is 12% in the combination of Plant / Vendor / Material and the tax code maintain as V1.
Scenario :- 2
Material :- BB27AH30KC10191-01
Plant :- 1000
Vendor :- 100029
Creating the PO for the above combination and maintained the tax code as V0.
The same FV11 is maintained for JMOP is 0% in the combination of Plant / Vendor / Material and the tax code maintain as V0.
For the scenario 2 the JMOP shows 12% in the Purchase order.
Please help to resolve the issue.
Regards,
Prabhakaran M