Re: What is the standard SAP planning process for this scenario?

$
0
0

Hi Ann,

 

Why don't you use the period lot size like WK with minimum lot size as 1000 for liquid sub assembly, Material X. So it will combine the requirement from product A,B and C in one planned order, System automatically combine these quantities into one planned orders from three different products with minimum lot size of 1000 will be soft constraint.

 

Regards,

R.Brahmankar