Hi, Mukesh,
I will explain it in more details.
GL - Repairs and Maintenance - Buildings
Cost Center Or Fund Center - Terminal Building
Now under this comibination, there are more than 1 ARC contracts. egs
ARC for Glass Doors Budget Rs.15 Lacs
ARC for Tank Clearning Budget Rs.10Lacs
Now if I upload budget for R&M Building - with Fund Center Terminal Budiling will it get uploaded as total Rs, 25 Lacs or I can see ARC for Glass Door Rs.15 Lacs, ARC for Tank Clearning Rs.10Lacs.
I want to track it individually that is I should know, against ARC for Glass door of Rs.15 Lacs what are the acuals and what is pending.
How do I achieve it? Please advise.... Thanks for all your time and your inputs are of great help to me...
Best Regards