Hi Manimaran, Hi Thamizh,
I tried to convert the SNP Planned orders into PP/DS Planned orders and then got the above mentioned errors. But both of your hints hit me on an idea:
By using CTM, SNP Planned orders are also created for customer Orders in the MTO Segment of Product view (transaction /SAPAPO/RRP3).
So I tried to convert some created SNP Planned Orders for the related components (which are in MTS Segment).
This SNP Planned Orders could be converted into PP/DS Planned Orders.
So I assume that conversion might be impossible because the SNP-Planned Orders are customer spesivic and because of this in the MTO Segment.
As far as I know SNP has got a problem with Make-To-Order Production in general.
Do you think that might be a possible explanation?
Thank you very much and kindest regards,